Mumbai
MRTS Corridor
-
V. K. Rane,
ex-MD, IRCON
1)
IMF report on Public – Private Partnership (PPP) dated
12th March 2004, states that “better management
in private sector and its capacity to innovate can lead
to increased efficiency, this in turn should translate
in to better quality and lower cost services” and it
further states that “Private financing can support increase
infrastructure investment without immediately adding
to government borrowing and debt, and can be source
of Govt. revenue.” However, in case of Mumbai
MRTS corridor under consideration, the project has neither
added to the Govt. revenues but instead the Govt. had
to pay Rs. 650 /- Crs, as VGF grant to the bidder, nor
have been able to provide any innovation or increased
efficiency, nor reduced the capital cost of the project.
The DMRC corridor, which was implemented on NON - PPP
/ EPC route, was executed in Delhi, at a capital cost
(without IDC) of Rs. 100 Crs per Km, while, the proposed
Mumbai Metro Corridor bid was accepted through PPP route,
at Rs. 200 Crs per Km, (including IDC)
2)
It was brought to the notice of the Chief Minister,
Chief Secretary of the Govt. of Maharashtra and MMRDA,
in my presentation, in 21st April 2005, that adoption
PPP route would unnecessarily inflate the capital cost,
to double the estimated cost of MMRDA.
3) BID PRICE & Viability Gap Funding (VGF)--
Against the estimated cost of Rs 1250 crores(without
cost of land)with around 300 crores of estimated VGF
subsidy, the contract was accepted at an abnormally
high price of Rs 2356 Crores with VGF subsidy of Rs
650 Crores (negotiated from Rs 1250 crors to Rs 650
crores reflecting the authenticity of bid price).This
is a sad reflection of the competency of MMRDA in preparation
of estimates or reliability of the bidder taking advantage
of limited (TWO Bidders) competition. (In an exactly
similar situation for Mumbai PUNE expressway, the PPP
route was rejected by the then the Govt. and the work
was completed by NON-PPP / EPC route in Rs 1250crors
against the Govt estimates of Rs 1500 Crores and contractors
bid price of Rs 3100 Crores (REL) via PPP route).
4) Abnormally High Price Quoted for Coaches--The
bidder has quoted the price of a SG coach at Rs 9 crores
per coach against the estimate price Rs 4.5 crores and
assessment of 108 coaches for VAG corridor. A BG coach
recently purchased by MRVC for Mumbai suburban section
from ICF, costs Rs 2. crores. One can realize the inflated
coach price of the bidder and accepted by MMRDA
as reasonable at Rs 9 crores each. Secondly,
if wider BG coaches were adopted, the number of coaches
required for operations for the entire concession period
would reduce to 72 as against 108 for SG This
would further reduce the Maintenance, operation and
energy costs there by reducing the VGF subsidy considerably.
5)
Automatic Train Control (ATC) & Automatic Tran Operation(
ATO) Signaling – This type of signaling is
required only for improving the frequency (Headway),
from 3min to 2 min. It is seen from traffic demand that
for the entire concession period, there is NO need to
operate at 2m frequency on this corridor. If
that is so, there was NO justification to insist on
provision of ATC & ATO signaling costing around
Rs 70 crores initially and replace 70 % of it after
16 years. This has unnecessarily inflated the cost of
VGF subsidy. This could have been avoided by
keeping provision in Rolling stock for future provision
of ATC as traffic demand increases. In fact for a country
like India, there is NO need for ATO ( Driverless Operation)
as in any case manning of Cab will be required for closing
doors. The computer simulation carried out for this
layout of the corridor indicates that, it is not feasible
to improve the frequency at lesser than 2.75 Min. while
the bidders have accepted, a provision of 2 min by installation
of ATC & ATO from the date of commissioning the
project. MMRDA and safety commissioner should ensured,
that trials are conducted at 2 min frequency, before
approving the fitness for commercial operations, on
this corridor. It is also not known, whether test runs
at 2 min frequency were carried out by DMRC on the Delhi
Metro Corridor in operation at present at 5 min frequency.
6) Alternative Bid for BG-- While inviting
alternative bids for BG, MMRDA deliberately did not
ask for bids with wider coaches for BG. This eliminated
competitive and capacity advantages for BG as compared
to SG. Thus, there was a deliberate and mischievous
attempt to eliminate capacity advantages of BG over
those of SG. The project cost of BG with wider
coaches, if compared on the basis of cost per unit carrying
capacity would be lower by 20 % than that for SG and
would further result in savings in energy and operation
costs, in view of the drastic reduction in the number
of coaches from 108 for SG to 72 for BG for VAG corridor.
Further it would cater for future traffic demand of
100 years rather than limiting it to 25 years as planned
today. For a given traffic demand, the length of the
train for BG, would be reduced, thereby considerably
reducing the land area required for the depot, due to
reduction in length of the trains, for given volume
of traffic, and would further reduce, the initial investments
in platform lengths and corresponding lengths for platform
covers. This would reduce the VGF amount quoted by the
bidders.
7)
The analyses of bid, shown below, actually quoted for
VGF corridor and accepted by MMRDA, would reveal a)
That the project cost has been exorbitantly inflated
by Rs 600 crs, and b) And refusal to reduce the initial
capital cost quoted by the bidder, (after negotiating
a reduction in VGF amount) was to ensure that, the entire
project could be executed, with the debt capital from
the lenders (Rs 1645 crs) and VGF grant of Rs 650 crs
together with 26 % equity of Govt. (both without interest)
of Rs 183 crs, making a total amounting to Rs 2478 crs.
This is much more than that required to actually execute
the project (Rs 1750 crs). This is without bidders equity
and gives surplus of Rs 728 crs (see table below).
ACCEPTED BID FOR MUMBAI METRO FOR VAG CORRIDOR
| a) |
Cost
of the Project |
Rs
2350 Cr |
| b) |
Viability
Gap Funding Originally asked for |
Rs
1250 Cr |
| c) |
Hence
acceptable cost of the project without VGF (a--b)
|
Rs
1100 Cr |
| C) |
Hence
acceptable cost of the project withour VGF (a--b) |
Rs
1100 Cr |
| d) |
Negotiated
VGF and accepted by bidder |
Rs
650 Cr |
| e) |
Thus
the reasonable cost of the project required for
execution (c+d) |
Rs
1750 Cr |
| f) |
Bidder
refused to accept reduction in project cost of |
Rs
2350 Cr |
| g) |
Hence
the project cost has been inflated by bidder (a-e)
= Rs 2350 Cr - Rs 1750 Cr |
Rs
600 Cr |
| h) |
At
70 to 30 debt equity ration, the debt available
from lenders id 0.70 X 2350 |
Rs
1645 Cr |
| i) |
Equity
at 30% of the Project cost is 0.30 X 2350 |
Rs
705 Cr |
| j) |
Equity
of the state govt at 26% of 705 (without interest) |
Rs
183.30 Cr |
| k) |
VGF
grant from the govt (without interest) |
Rs
650 Cr |
| l) |
Total
funds available to bidder (without interest) (j+k)
|
Rs
833 Cr |
| m) |
Total
funds available to Bidder (with interest on debt)=h |
Rs
1645 Cr |
| n) |
Total
funds available to bidder (without bidders equity)
= (l+m) |
Rs
2478 Cr |
| o) |
Total
funds required for execute the project |
Rs
1750 Cr |
| p) |
Execess
funds available with bidder without investment it
its equity (n-o) |
Rs
728 Cr |
• Thus
PPP projects are priced and executed without investment
of there own equity
• 30 % of profit is realized and the end of construction
period, in the name of risk provisions
• The return on equity during operation and maintenance
period is an additional bonus
• The company, however, carry the liability of
debt repayment for a loan repayment period.
8)
It will be seen from the above analyses of bid price
and acceptance of the same, that a proper evaluation,
implications and cannons of financial propriety have
not been observed, in award of contract, at such an
abnormally high price, without ensuring public financial
interest. It is presumed, that the auditor general will
certain look in these aspects with unbiased mind.
9)
Keeping in view, all the aspects mentioned above the
Gov. of Maharashtra, should modify the gauge from SG
to BG and adoption of wider coaches, from 3.20m to 3.66m
for Charkop-Bandra-Mankhurd heavy density corridor,
and make a provision for future increase from 8 coaches
to 10 to 12 coaches, so as to make a provision for accommodating
traffic demand for 75 to 100 years, in the interest
of the future generation of this city. I would like
to clarify that the 21 st century, best in the world
technology, has been adopted on BG (1676 mm) by BART
in San Francisco (USA), with 2 min service and 120m
sharp curves, and is being continued on BG for future
extensions, even though their main line systems are
on SG. It is further added that the high-speed lines
in Spain are on BG (1676mm) with the best in the world
technology. The TGV High Speed trains in France, do
negotiate tracks in Europe through different signaling
and traction systems. The advice to the state Govt.
that, the MRTS metro as proposed in Mumbai, cannot negotiate
/ run on the existing suburban / main line system is
incorrect. The entire technical, financial and legal
justifications given to the State Ministry, is based
on wrong statements and need to be urgently debated
further, with the representatives of the promoters of
BG in the overall of interest of this city’s planning
and its future commuters.
10)
With the Chief Minister’s dream of developing Mumbai
on Shanghai pattern by adoption of high-rise buildings
in the city, the density of population and the accelerated
rate of increase of commuters demand for MRTS, will
reach its inhuman crush capacity, on these corridors
in 15 to 20 years. The Govt. Therefore, should take
immediate steps, to review their present policy of adoption
of restricted width of coaches on SG, and provide for
adoption of wider coaches from future capacity considerations,
which would necessitated provision of BG track, in the
overall interest of the future generation.
SYNOPSIS The author analyses the economic considerations
in the award of the contract for the construction, maintenance
and operations of the elevated Versova-Andheri-Ghatkopar
Mass Rapid Transit Railway a stand alone corridor on
standard gauge via PPP route instead of EPC route, as
adopted for Delhi Metro. MMRDA took more than 3 years,
to finalize tenders and pre-award formalities, and ultimately
adopted a price, which resulted in double the estimated
cost for this project, with a limited competition of
two bidders prior to accepting the financial bid. The
cannons of financial propriety do not seem to have been
observed while awarding the contract on a 35-year concession
period. This was probably to prevent further delay,
and justified the exorbitantly high price. Though, it
is too late to make any changes at this stage, the Govt.
of Maharashtra need to look in to this aspect of a high
cost for SG limited capacity (with 3.2m wide) coaches
and make a provision for future adoption of BG with
higher capacity (3.66m wide) coaches, so that after
25 years, the capacity of this corridor can be suitability
increased, to meet future traffic demand. It is considered
essential to adopt BG with 3.66m wide coaches, for Charkop-Bandra-Mankhurd
heavy density corridor, and make necessary changes in
the bids, which are yet to be received and finalized.
